Introduction to insulation system
1. The VICP composite external formwork insulation system is formed by using VICP vacuum insulation external formwork as the outer formwork, pouring concrete on the inner side, and providing a protective layer on the outer side to form a non cavity composite insulation structure wall system.
2. Place the VICP vacuum insulated composite insulation outer template on the inside of the outer template, with the cast-in-place concrete outer wall as the base layer. The inner surface of the vacuum insulated composite insulation outer template is integrated with the cast-in-place concrete. After the template is removed, a protective layer is added on the outside of the vacuum insulated composite insulation non removable template to form a non cavity composite insulation structure wall system, abbreviated as VICP large mold built-in insulation system.